Аудиторская служба выявила недостатки в работе лесничеств в Акамасе 23 Июня 2025
Array ( [PREVIEW_PICTURE] => Array ( [ID] => 71660 [TIMESTAMP_X] => 23.06.2025 16:10:04 [MODULE_ID] => iblock [HEIGHT] => 733 [WIDTH] => 1100 [FILE_SIZE] => 232032 [CONTENT_TYPE] => image/jpeg [SUBDIR] => iblock/749 [FILE_NAME] => 749ae494f6e9350396ca5ead63c79de9.jpg [ORIGINAL_NAME] => feature-iole-A-new-retaining-wall-and-widened-road-as-works-have-begun-from-the-Paphos-end-of-the-Akamas-towards-Lara-bay.jpg [DESCRIPTION] => [HANDLER_ID] => [EXTERNAL_ID] => 8bf41e2bb3a671f16fb42a70c2fb2972 [~src] => [SRC] => /upload/iblock/749/749ae494f6e9350396ca5ead63c79de9.jpg [ALT] => Аудиторская служба выявила недостатки в работе лесничеств в Акамасе [TITLE] => Аудиторская служба выявила недостатки в работе лесничеств в Акамасе ) [~PREVIEW_PICTURE] => 71660 [ID] => 36362 [~ID] => 36362 [NAME] => Аудиторская служба выявила недостатки в работе лесничеств в Акамасе [~NAME] => Аудиторская служба выявила недостатки в работе лесничеств в Акамасе [IBLOCK_ID] => 2 [~IBLOCK_ID] => 2 [IBLOCK_SECTION_ID] => 2 [~IBLOCK_SECTION_ID] => 2 [DETAIL_TEXT] => Служба аудита в понедельник опубликовала [отчёт](https://www.audit.gov.cy/audit/audit.nsf/home/home?opendocument), в котором указала на бесхозяйственность и недосмотр департамента лесного хозяйства при управлении четырьмя контрактами в рамках плана устойчивого развития полуострова Акамас.

Служба аудита подчеркнула, что в задачи отчёта не входило изучение воздействия проекта на окружающую среду, которое в прошлом подвергалось широкой критике со стороны экологических групп.

«Хотя в рамках этого специального доклада не предполагалось изучение воздействия на окружающую среду Акамаса из-за строительных работ (…), похоже, существует разногласие между компетентными органами относительно того, были ли соблюдены условия окружающей среды», — говорится в отчёте.

Контракты были частью двух ключевых мероприятий в рамках плана, три из них касались модернизации дорожной сети, а четвёртый — создания 14 туристических узлов с основными объектами инфраструктуры, такими как парковки, туалеты и точки отдыха.

«Выводы аудита указывают на недостатки и упущения со стороны департамента лесного хозяйства, которые привели к значительным задержкам, увеличению расходов и неспособности защитить общественные интересы», — говорится в отчёте.

Согласно отчёту, цели проекта были плохо определены, что вызвало задержки и необходимость заключения дополнительного контракта на надзор. В отчёте также подверглось критике использование процедур присуждения контрактов без предварительной публикации для проектирования и надзора, что нарушает закон о закупках и в итоге приводит к нарушениям нормативных требований.

«Департамент лесного хозяйства не действовал своевременно, что привело к дополнительным претензиям со стороны подрядчика на сумму около 500 000 евро и потере 1 миллиона евро гарантий», — сообщила служба аудита, ссылаясь на планы по улучшению дорожной сети.

Что касается четырнадцати инфраструктурных узлов, в отчёте установлено, что контракты были разыграны до получения необходимой экологической оценки, что не позволило адекватно оценить потенциальное экологическое воздействие. Это впоследствии привело к вынужденным изменениям в проекте, что привело к увеличению стоимости на 135,3% с первоначальной оценки в 2,8 миллиона евро до 6,59 миллиона евро.

«Аудит подчеркнул необходимость существенного улучшения процедур департамента лесного хозяйства для обеспечения эффективного, экономичного и действенного осуществления проектов в лесном парке Акамас в соответствии с действующим законодательством», — подчеркнула служба аудита.

Департамент, присуждающий тендеры до получения необходимых экологических или других разрешений, столкнулся с рядом проблем, включая изменения в проекте после истечения контракта с консультантами, как указано в отчёте. Это в итоге привело к объявлению нового тендера на завершение незавершённых работ, который был запущен без предварительной публикации.

Кроме того, назначение инженера-контролёра после начала работ, как полагают, привело к задержкам и расходам, которых можно было бы избежать при более раннем планировании.

«В проекте по улучшению части основной дорожной сети специального лесного парка Акамас произошла значительная необоснованная задержка со стороны подрядчика», — говорится в отчёте, подчёркивая, что последний «с самого начала проекта явно не мог выполнить свои договорные обязательства».

В отчёте установлено, что департамент лесного хозяйства, несмотря на направление подрядчику предупредительных писем, не смог своевременно расторгнуть контракт. К моменту официального приостановления проекта прошло 94% времени, было выполнено 17,67% работ, подрядчик расторг контракт.

В отчёте перечислены несколько ошибок в соблюдении законодательных процедур, рекомендовано, чтобы департамент лесного хозяйства получал все необходимые разрешения до начала будущих проектных тендеров.

Служба аудита также рекомендовала улучшить управление контрактами, включая тщательный мониторинг хода выполнения проектов, своевременное рассмотрение запросов подрядчиков и регулярные отчёты о производительности.

Департамент лесного хозяйства позже в понедельник прокомментировал ситуацию, подчеркнув, что серьёзно относится к рекомендациям службы аудита.

«Департамент лесного хозяйства уже предпринял шаги по улучшению процедур продвижения новых строительных проектов и мониторинга соответствующих контрактов, а также содействует дальнейшему обучению персонала», — заявили в департаменте.

В департаменте заявили, что проекты Акамаса были разработаны «после многих лет усердных и напряжённых усилий по согласованию всех позиций различных служб», добавив, что контракт на строительство этапа А по улучшению дорожной сети в настоящее время находится в ведении соответствующих государственных органов, и поэтому «публичное заявление сделать невозможно».

Экологическое движение Кипра в понедельник днём прокомментировало отчёт, заявив, что он «подтверждает некомпетентность государства», добавив, что бесхозяйственность департамента лесного хозяйства «привела к растрате государственных средств».

Оно раскритиковало отчёт службы аудита за то, что в нём внимание уделяется исключительно аспекту финансового бесхозяйственности, при этом не рассматривается ущерб окружающей среде, причинённый самим проектом Акамас, утверждая, что это «большая трата государственных и природных ресурсов и большая угроза будущему среды обитания».

Ещё в январе дорожные работы в Национальном лесном парке Акамас были остановлены после того, как подрядчик Cyfield расторг контракт, сославшись на длительную приостановку работ и невыплаченные взносы.

Правительство также объявило о планах пересмотреть проект, пока в департаменте лесного хозяйства проводились дисциплинарные расследования. Этот инцидент стал очередным в череде отменённых контрактов, подписанных при предыдущей администрации. [~DETAIL_TEXT] => Служба аудита в понедельник опубликовала [отчёт](https://www.audit.gov.cy/audit/audit.nsf/home/home?opendocument), в котором указала на бесхозяйственность и недосмотр департамента лесного хозяйства при управлении четырьмя контрактами в рамках плана устойчивого развития полуострова Акамас.

Служба аудита подчеркнула, что в задачи отчёта не входило изучение воздействия проекта на окружающую среду, которое в прошлом подвергалось широкой критике со стороны экологических групп.

«Хотя в рамках этого специального доклада не предполагалось изучение воздействия на окружающую среду Акамаса из-за строительных работ (…), похоже, существует разногласие между компетентными органами относительно того, были ли соблюдены условия окружающей среды», — говорится в отчёте.

Контракты были частью двух ключевых мероприятий в рамках плана, три из них касались модернизации дорожной сети, а четвёртый — создания 14 туристических узлов с основными объектами инфраструктуры, такими как парковки, туалеты и точки отдыха.

«Выводы аудита указывают на недостатки и упущения со стороны департамента лесного хозяйства, которые привели к значительным задержкам, увеличению расходов и неспособности защитить общественные интересы», — говорится в отчёте.

Согласно отчёту, цели проекта были плохо определены, что вызвало задержки и необходимость заключения дополнительного контракта на надзор. В отчёте также подверглось критике использование процедур присуждения контрактов без предварительной публикации для проектирования и надзора, что нарушает закон о закупках и в итоге приводит к нарушениям нормативных требований.

«Департамент лесного хозяйства не действовал своевременно, что привело к дополнительным претензиям со стороны подрядчика на сумму около 500 000 евро и потере 1 миллиона евро гарантий», — сообщила служба аудита, ссылаясь на планы по улучшению дорожной сети.

Что касается четырнадцати инфраструктурных узлов, в отчёте установлено, что контракты были разыграны до получения необходимой экологической оценки, что не позволило адекватно оценить потенциальное экологическое воздействие. Это впоследствии привело к вынужденным изменениям в проекте, что привело к увеличению стоимости на 135,3% с первоначальной оценки в 2,8 миллиона евро до 6,59 миллиона евро.

«Аудит подчеркнул необходимость существенного улучшения процедур департамента лесного хозяйства для обеспечения эффективного, экономичного и действенного осуществления проектов в лесном парке Акамас в соответствии с действующим законодательством», — подчеркнула служба аудита.

Департамент, присуждающий тендеры до получения необходимых экологических или других разрешений, столкнулся с рядом проблем, включая изменения в проекте после истечения контракта с консультантами, как указано в отчёте. Это в итоге привело к объявлению нового тендера на завершение незавершённых работ, который был запущен без предварительной публикации.

Кроме того, назначение инженера-контролёра после начала работ, как полагают, привело к задержкам и расходам, которых можно было бы избежать при более раннем планировании.

«В проекте по улучшению части основной дорожной сети специального лесного парка Акамас произошла значительная необоснованная задержка со стороны подрядчика», — говорится в отчёте, подчёркивая, что последний «с самого начала проекта явно не мог выполнить свои договорные обязательства».

В отчёте установлено, что департамент лесного хозяйства, несмотря на направление подрядчику предупредительных писем, не смог своевременно расторгнуть контракт. К моменту официального приостановления проекта прошло 94% времени, было выполнено 17,67% работ, подрядчик расторг контракт.

В отчёте перечислены несколько ошибок в соблюдении законодательных процедур, рекомендовано, чтобы департамент лесного хозяйства получал все необходимые разрешения до начала будущих проектных тендеров.

Служба аудита также рекомендовала улучшить управление контрактами, включая тщательный мониторинг хода выполнения проектов, своевременное рассмотрение запросов подрядчиков и регулярные отчёты о производительности.

Департамент лесного хозяйства позже в понедельник прокомментировал ситуацию, подчеркнув, что серьёзно относится к рекомендациям службы аудита.

«Департамент лесного хозяйства уже предпринял шаги по улучшению процедур продвижения новых строительных проектов и мониторинга соответствующих контрактов, а также содействует дальнейшему обучению персонала», — заявили в департаменте.

В департаменте заявили, что проекты Акамаса были разработаны «после многих лет усердных и напряжённых усилий по согласованию всех позиций различных служб», добавив, что контракт на строительство этапа А по улучшению дорожной сети в настоящее время находится в ведении соответствующих государственных органов, и поэтому «публичное заявление сделать невозможно».

Экологическое движение Кипра в понедельник днём прокомментировало отчёт, заявив, что он «подтверждает некомпетентность государства», добавив, что бесхозяйственность департамента лесного хозяйства «привела к растрате государственных средств».

Оно раскритиковало отчёт службы аудита за то, что в нём внимание уделяется исключительно аспекту финансового бесхозяйственности, при этом не рассматривается ущерб окружающей среде, причинённый самим проектом Акамас, утверждая, что это «большая трата государственных и природных ресурсов и большая угроза будущему среды обитания».

Ещё в январе дорожные работы в Национальном лесном парке Акамас были остановлены после того, как подрядчик Cyfield расторг контракт, сославшись на длительную приостановку работ и невыплаченные взносы.

Правительство также объявило о планах пересмотреть проект, пока в департаменте лесного хозяйства проводились дисциплинарные расследования. Этот инцидент стал очередным в череде отменённых контрактов, подписанных при предыдущей администрации. [DETAIL_TEXT_TYPE] => html [~DETAIL_TEXT_TYPE] => html [PREVIEW_TEXT] => Служба аудита в понедельник опубликовала [отчёт](https://www.audit.gov.cy/audit/audit.nsf/home/home?opendocument... [~PREVIEW_TEXT] => Служба аудита в понедельник опубликовала [отчёт](https://www.audit.gov.cy/audit/audit.nsf/home/home?opendocument... [PREVIEW_TEXT_TYPE] => html [~PREVIEW_TEXT_TYPE] => html [DETAIL_PICTURE] => Array ( [SRC] => /upload/resize_cache/iblock/749/600_400_1/749ae494f6e9350396ca5ead63c79de9.jpg [WIDTH] => 600 [HEIGHT] => 399 ) [~DETAIL_PICTURE] => 71661 [ACTIVE_FROM] => 23.06.2025 16:10:00 [~ACTIVE_FROM] => 23.06.2025 16:10:00 [LIST_PAGE_URL] => /news/ [~LIST_PAGE_URL] => /news/ [DETAIL_PAGE_URL] => /news/society/audit-service-flags-forestry-departments-shortcomings-in-akamas/ [~DETAIL_PAGE_URL] => /news/society/audit-service-flags-forestry-departments-shortcomings-in-akamas/ [LANG_DIR] => / [~LANG_DIR] => / [CODE] => audit-service-flags-forestry-departments-shortcomings-in-akamas [~CODE] => audit-service-flags-forestry-departments-shortcomings-in-akamas [EXTERNAL_ID] => 36362 [~EXTERNAL_ID] => 36362 [IBLOCK_TYPE_ID] => news [~IBLOCK_TYPE_ID] => news [IBLOCK_CODE] => infoportal_news_s1 [~IBLOCK_CODE] => infoportal_news_s1 [IBLOCK_EXTERNAL_ID] => infoportal_news_s1 [~IBLOCK_EXTERNAL_ID] => infoportal_news_s1 [LID] => s1 [~LID] => s1 [NAV_RESULT] => [DISPLAY_ACTIVE_FROM] => 23 Июня 2025 [IPROPERTY_VALUES] => Array ( ) [FIELDS] => Array ( [PREVIEW_PICTURE] => Array ( [ID] => 71660 [TIMESTAMP_X] => 23.06.2025 16:10:04 [MODULE_ID] => iblock [HEIGHT] => 733 [WIDTH] => 1100 [FILE_SIZE] => 232032 [CONTENT_TYPE] => image/jpeg [SUBDIR] => iblock/749 [FILE_NAME] => 749ae494f6e9350396ca5ead63c79de9.jpg [ORIGINAL_NAME] => feature-iole-A-new-retaining-wall-and-widened-road-as-works-have-begun-from-the-Paphos-end-of-the-Akamas-towards-Lara-bay.jpg [DESCRIPTION] => [HANDLER_ID] => [EXTERNAL_ID] => 8bf41e2bb3a671f16fb42a70c2fb2972 [~src] => [SRC] => /upload/iblock/749/749ae494f6e9350396ca5ead63c79de9.jpg [ALT] => Аудиторская служба выявила недостатки в работе лесничеств в Акамасе [TITLE] => Аудиторская служба выявила недостатки в работе лесничеств в Акамасе ) ) [PROPERTIES] => Array ( [ORIGINAL_URL] => Array ( [ID] => 51 [TIMESTAMP_X] => 2017-10-03 13:37:23 [IBLOCK_ID] => 2 [NAME] => Ссылка на сайте-источнике [ACTIVE] => Y [SORT] => 10 [CODE] => ORIGINAL_URL [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 101318 [VALUE] => /2025/06/23/audit-service-flags-forestry-departments-shortcomings-in-akamas [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => /2025/06/23/audit-service-flags-forestry-departments-shortcomings-in-akamas [~DESCRIPTION] => [~NAME] => Ссылка на сайте-источнике [~DEFAULT_VALUE] => ) [THEME_EN] => Array ( [ID] => 280 [TIMESTAMP_X] => 2025-01-08 18:01:42 [IBLOCK_ID] => 2 [NAME] => Тема (en) [ACTIVE] => Y [SORT] => 20 [CODE] => THEME_EN [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => Y [SEARCHABLE] => N [FILTRABLE] => Y [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 101320 [VALUE] => Audit service flags forestry departments’ shortcomings in Akamas [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => Audit service flags forestry departments’ shortcomings in Akamas [~DESCRIPTION] => [~NAME] => Тема (en) [~DEFAULT_VALUE] => ) [TEXT_EN] => Array ( [ID] => 281 [TIMESTAMP_X] => 2025-01-08 18:01:42 [IBLOCK_ID] => 2 [NAME] => Текст новости (en) [ACTIVE] => Y [SORT] => 40 [CODE] => TEXT_EN [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => Y [SEARCHABLE] => N [FILTRABLE] => Y [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => HTML [USER_TYPE_SETTINGS] => Array ( [height] => 200 ) [HINT] => [PROPERTY_VALUE_ID] => 101321 [VALUE] => Array ( [TEXT] => The audit service on Monday published [a report](https://www.audit.gov.cy/audit/audit.nsf/home/home?opendocument) flagging mismanagement and oversights by the forestry department in managing four contracts as part of the sustainable development plan for the Akamas peninsula. The audit service stressed that the remit of the report did not include the environmental impact of the project, which had in the past drawn up broad criticism by environmental groups. “Although it was not part of this special report to investigate the environmental impact on Akamas due to construction work, (…) there seems to be a division between the competent bodies on whether or not environmental conditions have been complied with,” the report said. The contracts were part of two key actions under the plan, three of them concerning road network upgrades and a fourth involving the creation of 14 visitor nodes with basic facilities such as parking, toilets, and refreshment points. “The audit findings highlight shortcomings and omissions by the forestry department that resulted in significant delays, increased costs and a failure to protect the public interest,” the report read. According to the report, project objectives were poorly defined, causing delays and the need for an additional supervision contract. The report also criticised the use of award procedures without prior publication for design and supervision, breaching procurement law and eventually leading to regulatory violations. “The forestry department did not act in a timely manner, resulting in additional claims on behalf of the contractor of around €500,000 and the loss of €1 million in guarantees,” the audit service said, referring to the road network improvement plans. Regarding the fourteen infrastructure nodes, the report found that contracts were tendered before securing the required environmental assessment, failing to adequately evaluate potential ecological impact. This later resulted in forced design changes, which came at a 135.3 per cent cost increase from an initial estimate of €2.8 million to €6.59 million. “The audit highlighted the need for substantial improvement of the procedures of the forestry department to ensure the effective, economical and efficient implementation of projects in the Akamas forest park in compliance with the relevant legislation,” the audit service stressed. The department awarding tenders before securing the necessary environmental or other approvals led to several problems, including changes to the project design after the consultants’ contract had expired, the report found. This eventually led to issuing of a new tender for the completion of the unfinished works, launched without prior publication. Additionally, the appointing of a supervising engineer after work began is believed to have caused delays and costs that might have been avoided with earlier planning. “In the project to improve part of the main road network of the Akamas special forest park, there was a significant unjustified delay on the part of the contractor,” the report said, stressing that the latter was “clearly, from the beginning of the project, unable to comply with his contractual obligations”. The report found that the forestry department, despite issuing warning letters to the contractor, failed to terminate the contract in a timely manner. By the time the project was officially suspended, 94 per cent of the time had passed with 17.67 per cent of the work done, the contractor cancelled the contract. The report listed several mistakes in following legal procedures, recommending that the forestry department secured all necessary approvals before launching future project tenders. The audit service also advised improved contract management, including close monitoring of progress during projects, the timely handling of contractor requests, and regular performance reports. The forestry department later on Monday commented on the matter, stressing that it took the audit service’s recommendations seriously. “The forestry department has already taken steps to improve the procedures for promoting new construction projects and monitoring relevant contracts, while also promoting further training of personnel,” the department said. The department said the Akamas projects were designed “after many years of diligent and arduous efforts to reconcile all the positions of the various services.”, adding that the Phase A construction contract for road network improvements was currently being handled by the relevant state authorities, and therefore “no public statement can be made.” The Cyprus Ecological Movement on Monday afternoon commented on the report saying it “confirms state incompetence”, adding that the forestry departments mismanagement had “led to the embezzlement of public funds.” It criticised the audit service’s report for focusing solely on the aspect of financial mismanagement, while failing to address environmental damage caused by the Akamas project itself, arguing it was “a great waste of public and natural resources and a great threat to the future of the habitat.” Back in January, roadworks in the Akamas National Forest Park were halted after the contractor, Cyfield, had terminated the contract citing prolonged suspension of work and unpaid dues. The government had equally announced plans to revise the project, while disciplinary investigations into the forestry department were underway. The incident added to a string of cancelled contracts signed under the previous administration. [TYPE] => HTML ) [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => Array ( [TEXT] => The audit service on Monday published [a report](https://www.audit.gov.cy/audit/audit.nsf/home/home?opendocument) flagging mismanagement and oversights by the forestry department in managing four contracts as part of the sustainable development plan for the Akamas peninsula. The audit service stressed that the remit of the report did not include the environmental impact of the project, which had in the past drawn up broad criticism by environmental groups. “Although it was not part of this special report to investigate the environmental impact on Akamas due to construction work, (…) there seems to be a division between the competent bodies on whether or not environmental conditions have been complied with,” the report said. The contracts were part of two key actions under the plan, three of them concerning road network upgrades and a fourth involving the creation of 14 visitor nodes with basic facilities such as parking, toilets, and refreshment points. “The audit findings highlight shortcomings and omissions by the forestry department that resulted in significant delays, increased costs and a failure to protect the public interest,” the report read. According to the report, project objectives were poorly defined, causing delays and the need for an additional supervision contract. The report also criticised the use of award procedures without prior publication for design and supervision, breaching procurement law and eventually leading to regulatory violations. “The forestry department did not act in a timely manner, resulting in additional claims on behalf of the contractor of around €500,000 and the loss of €1 million in guarantees,” the audit service said, referring to the road network improvement plans. Regarding the fourteen infrastructure nodes, the report found that contracts were tendered before securing the required environmental assessment, failing to adequately evaluate potential ecological impact. This later resulted in forced design changes, which came at a 135.3 per cent cost increase from an initial estimate of €2.8 million to €6.59 million. “The audit highlighted the need for substantial improvement of the procedures of the forestry department to ensure the effective, economical and efficient implementation of projects in the Akamas forest park in compliance with the relevant legislation,” the audit service stressed. The department awarding tenders before securing the necessary environmental or other approvals led to several problems, including changes to the project design after the consultants’ contract had expired, the report found. This eventually led to issuing of a new tender for the completion of the unfinished works, launched without prior publication. Additionally, the appointing of a supervising engineer after work began is believed to have caused delays and costs that might have been avoided with earlier planning. “In the project to improve part of the main road network of the Akamas special forest park, there was a significant unjustified delay on the part of the contractor,” the report said, stressing that the latter was “clearly, from the beginning of the project, unable to comply with his contractual obligations”. The report found that the forestry department, despite issuing warning letters to the contractor, failed to terminate the contract in a timely manner. By the time the project was officially suspended, 94 per cent of the time had passed with 17.67 per cent of the work done, the contractor cancelled the contract. The report listed several mistakes in following legal procedures, recommending that the forestry department secured all necessary approvals before launching future project tenders. The audit service also advised improved contract management, including close monitoring of progress during projects, the timely handling of contractor requests, and regular performance reports. The forestry department later on Monday commented on the matter, stressing that it took the audit service’s recommendations seriously. “The forestry department has already taken steps to improve the procedures for promoting new construction projects and monitoring relevant contracts, while also promoting further training of personnel,” the department said. The department said the Akamas projects were designed “after many years of diligent and arduous efforts to reconcile all the positions of the various services.”, adding that the Phase A construction contract for road network improvements was currently being handled by the relevant state authorities, and therefore “no public statement can be made.” The Cyprus Ecological Movement on Monday afternoon commented on the report saying it “confirms state incompetence”, adding that the forestry departments mismanagement had “led to the embezzlement of public funds.” It criticised the audit service’s report for focusing solely on the aspect of financial mismanagement, while failing to address environmental damage caused by the Akamas project itself, arguing it was “a great waste of public and natural resources and a great threat to the future of the habitat.” Back in January, roadworks in the Akamas National Forest Park were halted after the contractor, Cyfield, had terminated the contract citing prolonged suspension of work and unpaid dues. The government had equally announced plans to revise the project, while disciplinary investigations into the forestry department were underway. The incident added to a string of cancelled contracts signed under the previous administration. [TYPE] => HTML ) [~DESCRIPTION] => [~NAME] => Текст новости (en) [~DEFAULT_VALUE] => ) [FORUM_MESSAGE_CNT] => Array ( [ID] => 2 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Количество комментариев к элементу [ACTIVE] => Y [SORT] => 500 [CODE] => FORUM_MESSAGE_CNT [DEFAULT_VALUE] => [PROPERTY_TYPE] => N [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 63 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Количество комментариев к элементу [~DEFAULT_VALUE] => ) [FORUM_TOPIC_ID] => Array ( [ID] => 3 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Тема форума для комментариев [ACTIVE] => Y [SORT] => 500 [CODE] => FORUM_TOPIC_ID [DEFAULT_VALUE] => [PROPERTY_TYPE] => N [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 62 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Тема форума для комментариев [~DEFAULT_VALUE] => ) [MORE_PHOTO] => Array ( [ID] => 4 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Изображения [ACTIVE] => Y [SORT] => 500 [CODE] => MORE_PHOTO [DEFAULT_VALUE] => [PROPERTY_TYPE] => F [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => Y [XML_ID] => 58 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Изображения [~DEFAULT_VALUE] => ) [PARTMAIN] => Array ( [ID] => 5 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Главная новость раздела [ACTIVE] => Y [SORT] => 500 [CODE] => PARTMAIN [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => C [MULTIPLE] => N [XML_ID] => 56 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [VALUE_ENUM_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Главная новость раздела [~DEFAULT_VALUE] => ) [MAIN] => Array ( [ID] => 6 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Главная новость главной страницы [ACTIVE] => Y [SORT] => 500 [CODE] => MAIN [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => C [MULTIPLE] => N [XML_ID] => 55 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [VALUE_ENUM_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Главная новость главной страницы [~DEFAULT_VALUE] => ) [THEME] => Array ( [ID] => 7 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Тема [ACTIVE] => Y [SORT] => 500 [CODE] => THEME [DEFAULT_VALUE] => [PROPERTY_TYPE] => E [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => Y [XML_ID] => 54 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 1 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => EAutocomplete [USER_TYPE_SETTINGS] => Array ( [VIEW] => A [SHOW_ADD] => Y [MAX_WIDTH] => 250 [MIN_HEIGHT] => 24 [MAX_HEIGHT] => 1000 [BAN_SYM] => ,; [REP_SYM] => [OTHER_REP_SYM] => [IBLOCK_MESS] => Y ) [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Тема [~DEFAULT_VALUE] => ) [LINK_SOURCE] => Array ( [ID] => 8 [TIMESTAMP_X] => 2015-05-25 16:39:08 [IBLOCK_ID] => 2 [NAME] => Источник [ACTIVE] => Y [SORT] => 500 [CODE] => LINK_SOURCE [DEFAULT_VALUE] => russiancyprus [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 53 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 101317 [VALUE] => cyprus-mail.com [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => cyprus-mail.com [~DESCRIPTION] => [~NAME] => Источник [~DEFAULT_VALUE] => russiancyprus ) [IS_SENT_TO_CHANEL] => Array ( [ID] => 167 [TIMESTAMP_X] => 2020-06-25 17:42:19 [IBLOCK_ID] => 2 [NAME] => Is sent to telegram [ACTIVE] => Y [SORT] => 500 [CODE] => IS_SENT_TO_CHANEL [DEFAULT_VALUE] => [PROPERTY_TYPE] => N [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 101332 [VALUE] => 1 [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => 1 [~DESCRIPTION] => [~NAME] => Is sent to telegram [~DEFAULT_VALUE] => ) [YANDEX_TASK_ID_THEME] => Array ( [ID] => 285 [TIMESTAMP_X] => 2025-01-20 21:25:08 [IBLOCK_ID] => 2 [NAME] => YANDEX TASK ID FOR THEME [ACTIVE] => Y [SORT] => 900 [CODE] => YANDEX_TASK_ID_THEME [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 101322 [VALUE] => d7qr86r366qf0s6vm1u5 [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => d7qr86r366qf0s6vm1u5 [~DESCRIPTION] => [~NAME] => YANDEX TASK ID FOR THEME [~DEFAULT_VALUE] => ) [YANDEX_TASK_ID] => Array ( [ID] => 284 [TIMESTAMP_X] => 2025-01-20 20:37:32 [IBLOCK_ID] => 2 [NAME] => YANDEX TASK ID [ACTIVE] => Y [SORT] => 1000 [CODE] => YANDEX_TASK_ID [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 101323 [VALUE] => d7qhrhojspuaehsa653a [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => d7qhrhojspuaehsa653a [~DESCRIPTION] => [~NAME] => YANDEX TASK ID [~DEFAULT_VALUE] => ) ) [DISPLAY_PROPERTIES] => Array ( ) [IBLOCK] => Array ( [ID] => 2 [~ID] => 2 [TIMESTAMP_X] => 20.01.2025 22:57:06 [~TIMESTAMP_X] => 20.01.2025 22:57:06 [IBLOCK_TYPE_ID] => news [~IBLOCK_TYPE_ID] => news [LID] => s1 [~LID] => s1 [CODE] => infoportal_news_s1 [~CODE] => infoportal_news_s1 [NAME] => Новости [~NAME] => Новости [ACTIVE] => Y [~ACTIVE] => Y [SORT] => 500 [~SORT] => 500 [LIST_PAGE_URL] => /news/ [~LIST_PAGE_URL] => /news/ [DETAIL_PAGE_URL] => #SITE_DIR#/news/#SECTION_CODE#/#CODE#/ [~DETAIL_PAGE_URL] => #SITE_DIR#/news/#SECTION_CODE#/#CODE#/ [SECTION_PAGE_URL] => #SITE_DIR#/news/#CODE#/ [~SECTION_PAGE_URL] => #SITE_DIR#/news/#CODE#/ [PICTURE] => [~PICTURE] => [DESCRIPTION] => [~DESCRIPTION] => [DESCRIPTION_TYPE] => text [~DESCRIPTION_TYPE] => text [RSS_TTL] => 24 [~RSS_TTL] => 24 [RSS_ACTIVE] => Y [~RSS_ACTIVE] => Y [RSS_FILE_ACTIVE] => N [~RSS_FILE_ACTIVE] => N [RSS_FILE_LIMIT] => 0 [~RSS_FILE_LIMIT] => 0 [RSS_FILE_DAYS] => 0 [~RSS_FILE_DAYS] => 0 [RSS_YANDEX_ACTIVE] => N [~RSS_YANDEX_ACTIVE] => N [XML_ID] => infoportal_news_s1 [~XML_ID] => infoportal_news_s1 [TMP_ID] => adf9113ce97738184efe133d53e3d656 [~TMP_ID] => adf9113ce97738184efe133d53e3d656 [INDEX_ELEMENT] => Y [~INDEX_ELEMENT] => Y [INDEX_SECTION] => N [~INDEX_SECTION] => N [WORKFLOW] => N [~WORKFLOW] => N [BIZPROC] => N [~BIZPROC] => N [SECTION_CHOOSER] => L [~SECTION_CHOOSER] => L [LIST_MODE] => [~LIST_MODE] => [RIGHTS_MODE] => S [~RIGHTS_MODE] => S [SECTION_PROPERTY] => [~SECTION_PROPERTY] => [PROPERTY_INDEX] => [~PROPERTY_INDEX] => [VERSION] => 1 [~VERSION] => 1 [LAST_CONV_ELEMENT] => 0 [~LAST_CONV_ELEMENT] => 0 [SOCNET_GROUP_ID] => [~SOCNET_GROUP_ID] => [EDIT_FILE_BEFORE] => [~EDIT_FILE_BEFORE] => [EDIT_FILE_AFTER] => [~EDIT_FILE_AFTER] => [SECTIONS_NAME] => Разделы [~SECTIONS_NAME] => Разделы [SECTION_NAME] => Раздел [~SECTION_NAME] => Раздел [ELEMENTS_NAME] => Новости [~ELEMENTS_NAME] => Новости [ELEMENT_NAME] => Новость [~ELEMENT_NAME] => Новость [EXTERNAL_ID] => infoportal_news_s1 [~EXTERNAL_ID] => infoportal_news_s1 [LANG_DIR] => / [~LANG_DIR] => / [SERVER_NAME] => russiancyprus.news [~SERVER_NAME] => russiancyprus.news ) [SECTION] => Array ( [PATH] => Array ( [0] => Array ( [ID] => 2 [~ID] => 2 [TIMESTAMP_X] => 2025-01-20 22:54:27 [~TIMESTAMP_X] => 2025-01-20 22:54:27 [MODIFIED_BY] => 1 [~MODIFIED_BY] => 1 [DATE_CREATE] => 2015-04-24 10:15:32 [~DATE_CREATE] => 2015-04-24 10:15:32 [CREATED_BY] => 1 [~CREATED_BY] => 1 [IBLOCK_ID] => 2 [~IBLOCK_ID] => 2 [IBLOCK_SECTION_ID] => [~IBLOCK_SECTION_ID] => [ACTIVE] => Y [~ACTIVE] => Y [GLOBAL_ACTIVE] => Y [~GLOBAL_ACTIVE] => Y [SORT] => 5 [~SORT] => 5 [NAME] => Общество и политика [~NAME] => Общество и политика [PICTURE] => [~PICTURE] => [LEFT_MARGIN] => 1 [~LEFT_MARGIN] => 1 [RIGHT_MARGIN] => 2 [~RIGHT_MARGIN] => 2 [DEPTH_LEVEL] => 1 [~DEPTH_LEVEL] => 1 [DESCRIPTION] => [~DESCRIPTION] => [DESCRIPTION_TYPE] => text [~DESCRIPTION_TYPE] => text [SEARCHABLE_CONTENT] => Общество и политика [~SEARCHABLE_CONTENT] => Общество и политика [CODE] => society [~CODE] => society [XML_ID] => 111 [~XML_ID] => 111 [TMP_ID] => [~TMP_ID] => [DETAIL_PICTURE] => [~DETAIL_PICTURE] => [SOCNET_GROUP_ID] => [~SOCNET_GROUP_ID] => [LIST_PAGE_URL] => /news/ [~LIST_PAGE_URL] => /news/ [SECTION_PAGE_URL] => /news/society/ [~SECTION_PAGE_URL] => /news/society/ [IBLOCK_TYPE_ID] => news [~IBLOCK_TYPE_ID] => news [IBLOCK_CODE] => infoportal_news_s1 [~IBLOCK_CODE] => infoportal_news_s1 [IBLOCK_EXTERNAL_ID] => infoportal_news_s1 [~IBLOCK_EXTERNAL_ID] => infoportal_news_s1 [EXTERNAL_ID] => 111 [~EXTERNAL_ID] => 111 [IPROPERTY_VALUES] => Array ( ) ) ) ) [SECTION_URL] => /news/society/ [ITEMS_THEME] => Array ( ) )
Аудиторская служба выявила недостатки в работе лесничеств в Акамасе
Служба аудита в понедельник опубликовала [отчёт](https://www.audit.gov.cy/audit/audit.nsf/home/home?opendocument), в котором указала на бесхозяйственность и недосмотр департамента лесного хозяйства при управлении четырьмя контрактами в рамках плана устойчивого развития полуострова Акамас.

Служба аудита подчеркнула, что в задачи отчёта не входило изучение воздействия проекта на окружающую среду, которое в прошлом подвергалось широкой критике со стороны экологических групп.

«Хотя в рамках этого специального доклада не предполагалось изучение воздействия на окружающую среду Акамаса из-за строительных работ (…), похоже, существует разногласие между компетентными органами относительно того, были ли соблюдены условия окружающей среды», — говорится в отчёте.

Контракты были частью двух ключевых мероприятий в рамках плана, три из них касались модернизации дорожной сети, а четвёртый — создания 14 туристических узлов с основными объектами инфраструктуры, такими как парковки, туалеты и точки отдыха.

«Выводы аудита указывают на недостатки и упущения со стороны департамента лесного хозяйства, которые привели к значительным задержкам, увеличению расходов и неспособности защитить общественные интересы», — говорится в отчёте.

Согласно отчёту, цели проекта были плохо определены, что вызвало задержки и необходимость заключения дополнительного контракта на надзор. В отчёте также подверглось критике использование процедур присуждения контрактов без предварительной публикации для проектирования и надзора, что нарушает закон о закупках и в итоге приводит к нарушениям нормативных требований.

«Департамент лесного хозяйства не действовал своевременно, что привело к дополнительным претензиям со стороны подрядчика на сумму около 500 000 евро и потере 1 миллиона евро гарантий», — сообщила служба аудита, ссылаясь на планы по улучшению дорожной сети.

Что касается четырнадцати инфраструктурных узлов, в отчёте установлено, что контракты были разыграны до получения необходимой экологической оценки, что не позволило адекватно оценить потенциальное экологическое воздействие. Это впоследствии привело к вынужденным изменениям в проекте, что привело к увеличению стоимости на 135,3% с первоначальной оценки в 2,8 миллиона евро до 6,59 миллиона евро.

«Аудит подчеркнул необходимость существенного улучшения процедур департамента лесного хозяйства для обеспечения эффективного, экономичного и действенного осуществления проектов в лесном парке Акамас в соответствии с действующим законодательством», — подчеркнула служба аудита.

Департамент, присуждающий тендеры до получения необходимых экологических или других разрешений, столкнулся с рядом проблем, включая изменения в проекте после истечения контракта с консультантами, как указано в отчёте. Это в итоге привело к объявлению нового тендера на завершение незавершённых работ, который был запущен без предварительной публикации.

Кроме того, назначение инженера-контролёра после начала работ, как полагают, привело к задержкам и расходам, которых можно было бы избежать при более раннем планировании.

«В проекте по улучшению части основной дорожной сети специального лесного парка Акамас произошла значительная необоснованная задержка со стороны подрядчика», — говорится в отчёте, подчёркивая, что последний «с самого начала проекта явно не мог выполнить свои договорные обязательства».

В отчёте установлено, что департамент лесного хозяйства, несмотря на направление подрядчику предупредительных писем, не смог своевременно расторгнуть контракт. К моменту официального приостановления проекта прошло 94% времени, было выполнено 17,67% работ, подрядчик расторг контракт.

В отчёте перечислены несколько ошибок в соблюдении законодательных процедур, рекомендовано, чтобы департамент лесного хозяйства получал все необходимые разрешения до начала будущих проектных тендеров.

Служба аудита также рекомендовала улучшить управление контрактами, включая тщательный мониторинг хода выполнения проектов, своевременное рассмотрение запросов подрядчиков и регулярные отчёты о производительности.

Департамент лесного хозяйства позже в понедельник прокомментировал ситуацию, подчеркнув, что серьёзно относится к рекомендациям службы аудита.

«Департамент лесного хозяйства уже предпринял шаги по улучшению процедур продвижения новых строительных проектов и мониторинга соответствующих контрактов, а также содействует дальнейшему обучению персонала», — заявили в департаменте.

В департаменте заявили, что проекты Акамаса были разработаны «после многих лет усердных и напряжённых усилий по согласованию всех позиций различных служб», добавив, что контракт на строительство этапа А по улучшению дорожной сети в настоящее время находится в ведении соответствующих государственных органов, и поэтому «публичное заявление сделать невозможно».

Экологическое движение Кипра в понедельник днём прокомментировало отчёт, заявив, что он «подтверждает некомпетентность государства», добавив, что бесхозяйственность департамента лесного хозяйства «привела к растрате государственных средств».

Оно раскритиковало отчёт службы аудита за то, что в нём внимание уделяется исключительно аспекту финансового бесхозяйственности, при этом не рассматривается ущерб окружающей среде, причинённый самим проектом Акамас, утверждая, что это «большая трата государственных и природных ресурсов и большая угроза будущему среды обитания».

Ещё в январе дорожные работы в Национальном лесном парке Акамас были остановлены после того, как подрядчик Cyfield расторг контракт, сославшись на длительную приостановку работ и невыплаченные взносы.

Правительство также объявило о планах пересмотреть проект, пока в департаменте лесного хозяйства проводились дисциплинарные расследования. Этот инцидент стал очередным в череде отменённых контрактов, подписанных при предыдущей администрации.

Материал подготовлен с использованием издания Cyprus-mail.com с обработкой ИИ.
Источник изображения: Cyprus-mail.com