Незаконный сброс отходов во время строительства полицейского участка 16 Декабря 2025
Array ( [PREVIEW_PICTURE] => Array ( [ID] => 79486 [TIMESTAMP_X] => 16.12.2025 13:20:03 [MODULE_ID] => iblock [HEIGHT] => 733 [WIDTH] => 1100 [FILE_SIZE] => 293188 [CONTENT_TYPE] => image/jpeg [SUBDIR] => iblock/889 [FILE_NAME] => 889ab0bd1491417e8c47100659d10443.jpg [ORIGINAL_NAME] => debris-5590900_960_720.jpg [DESCRIPTION] => [HANDLER_ID] => [EXTERNAL_ID] => 85e93f10811aa9b39866fc2e49ca98aa [~src] => [SRC] => /upload/iblock/889/889ab0bd1491417e8c47100659d10443.jpg [ALT] => Незаконный сброс отходов во время строительства полицейского участка [TITLE] => Незаконный сброс отходов во время строительства полицейского участка ) [~PREVIEW_PICTURE] => 79486 [ID] => 40314 [~ID] => 40314 [NAME] => Незаконный сброс отходов во время строительства полицейского участка [~NAME] => Незаконный сброс отходов во время строительства полицейского участка [IBLOCK_ID] => 2 [~IBLOCK_ID] => 2 [IBLOCK_SECTION_ID] => 2 [~IBLOCK_SECTION_ID] => 2 [DETAIL_TEXT] => Согласно отчёту, опубликованному во вторник аудиторской службой, строительный мусор был незаконно выброшен во время строительства полицейского участка в горной деревне Эвриху в Троодосе.

В отчёте говорится, что компания, заключившая контракт на строительство полицейского участка, имела «первоначальное обязательство» перевозить большую часть отходов на «лицензированный объект», при этом ей было разрешено «управлять частью объёма отходов у источника» и использовать их «в основном в качестве материала для свалок».

Однако, согласно отчёту, согласно информации и документам, полученным из департамента общественных работ, «ясно видно, что подрядчик пересмотрел способ управления» строительными отходами на этапе выполнения проекта.

«Подрядчик имел право повторно использовать строительный мусор для засыпки только в пределах строительной площадки и не размещать его на прилегающих территориях», — говорится в отчёте.

Несмотря на это, часть отходов была выброшена на прилегающем участке, который принадлежит местному школьному совету.

В отчёте подчёркивается, что в соответствии с инструкциями департамента окружающей среды, произведённые отходы «могут быть использованы для засыпки… в местах, где проводились раскопки, или по инженерным причинам в ландшафтной архитектуре при определённых условиях», но эти условия не были выполнены при строительстве полицейского участка.

Расследование департамента окружающей среды показало, что «из общего объёма количества щебня, образовавшегося в результате земляных работ, 6 547 кубических метров остались в качестве остатка того, что было раскопано».

Кроме того, из этого количества 6 384 кубических метра отходов были выброшены на прилегающие территории.

В отчёте говорится, что департамент окружающей среды установил: из-за укладки асфальта на территории полицейского участка и «наличия там отходов с прошлого» возникла «трудность в вывозе отходов, размещённых до и во время строительства» полицейского участка.

Таким образом, по словам ведомства, «вывезти отходы и восстановить территорию невозможно».

Кроме того, в отчёте указано, что департамент окружающей среды установил: выброшенные материалы «подходят» для того, чтобы их оставили на месте, и что для доказательства этого были проведены «необходимые лабораторные испытания», и по этой причине департамент «считает, что вывоз строительного мусора и восстановление территории не требуется».

Затем аудиторская служба выразила сожаление по поводу «значительной задержки» в принятии департаментом окружающей среды решения о расследовании этого вопроса, заявив, что обвинения были «первоначально выдвинуты» ещё в январе 2022 года, но департамент окружающей среды не сообщил о результатах расследования до 27 октября этого года.

Также в отчёте говорится, что во время строительства полицейского участка план правительства по обращению с отходами не соблюдался, и объём образующихся отходов был подтверждён только постфактум. [~DETAIL_TEXT] => Согласно отчёту, опубликованному во вторник аудиторской службой, строительный мусор был незаконно выброшен во время строительства полицейского участка в горной деревне Эвриху в Троодосе.

В отчёте говорится, что компания, заключившая контракт на строительство полицейского участка, имела «первоначальное обязательство» перевозить большую часть отходов на «лицензированный объект», при этом ей было разрешено «управлять частью объёма отходов у источника» и использовать их «в основном в качестве материала для свалок».

Однако, согласно отчёту, согласно информации и документам, полученным из департамента общественных работ, «ясно видно, что подрядчик пересмотрел способ управления» строительными отходами на этапе выполнения проекта.

«Подрядчик имел право повторно использовать строительный мусор для засыпки только в пределах строительной площадки и не размещать его на прилегающих территориях», — говорится в отчёте.

Несмотря на это, часть отходов была выброшена на прилегающем участке, который принадлежит местному школьному совету.

В отчёте подчёркивается, что в соответствии с инструкциями департамента окружающей среды, произведённые отходы «могут быть использованы для засыпки… в местах, где проводились раскопки, или по инженерным причинам в ландшафтной архитектуре при определённых условиях», но эти условия не были выполнены при строительстве полицейского участка.

Расследование департамента окружающей среды показало, что «из общего объёма количества щебня, образовавшегося в результате земляных работ, 6 547 кубических метров остались в качестве остатка того, что было раскопано».

Кроме того, из этого количества 6 384 кубических метра отходов были выброшены на прилегающие территории.

В отчёте говорится, что департамент окружающей среды установил: из-за укладки асфальта на территории полицейского участка и «наличия там отходов с прошлого» возникла «трудность в вывозе отходов, размещённых до и во время строительства» полицейского участка.

Таким образом, по словам ведомства, «вывезти отходы и восстановить территорию невозможно».

Кроме того, в отчёте указано, что департамент окружающей среды установил: выброшенные материалы «подходят» для того, чтобы их оставили на месте, и что для доказательства этого были проведены «необходимые лабораторные испытания», и по этой причине департамент «считает, что вывоз строительного мусора и восстановление территории не требуется».

Затем аудиторская служба выразила сожаление по поводу «значительной задержки» в принятии департаментом окружающей среды решения о расследовании этого вопроса, заявив, что обвинения были «первоначально выдвинуты» ещё в январе 2022 года, но департамент окружающей среды не сообщил о результатах расследования до 27 октября этого года.

Также в отчёте говорится, что во время строительства полицейского участка план правительства по обращению с отходами не соблюдался, и объём образующихся отходов был подтверждён только постфактум. [DETAIL_TEXT_TYPE] => html [~DETAIL_TEXT_TYPE] => html [PREVIEW_TEXT] => Согласно отчёту, опубликованному во вторник аудиторской службой, строительный мусор... [~PREVIEW_TEXT] => Согласно отчёту, опубликованному во вторник аудиторской службой, строительный мусор... [PREVIEW_TEXT_TYPE] => html [~PREVIEW_TEXT_TYPE] => html [DETAIL_PICTURE] => Array ( [SRC] => /upload/resize_cache/iblock/889/600_400_1/889ab0bd1491417e8c47100659d10443.jpg [WIDTH] => 600 [HEIGHT] => 399 ) [~DETAIL_PICTURE] => 79487 [ACTIVE_FROM] => 16.12.2025 13:20:00 [~ACTIVE_FROM] => 16.12.2025 13:20:00 [LIST_PAGE_URL] => /news/ [~LIST_PAGE_URL] => /news/ [DETAIL_PAGE_URL] => /news/society/waste-illegally-dumped-during-construction-of-police-station/ [~DETAIL_PAGE_URL] => /news/society/waste-illegally-dumped-during-construction-of-police-station/ [LANG_DIR] => / [~LANG_DIR] => / [CODE] => waste-illegally-dumped-during-construction-of-police-station [~CODE] => waste-illegally-dumped-during-construction-of-police-station [EXTERNAL_ID] => 40314 [~EXTERNAL_ID] => 40314 [IBLOCK_TYPE_ID] => news [~IBLOCK_TYPE_ID] => news [IBLOCK_CODE] => infoportal_news_s1 [~IBLOCK_CODE] => infoportal_news_s1 [IBLOCK_EXTERNAL_ID] => infoportal_news_s1 [~IBLOCK_EXTERNAL_ID] => infoportal_news_s1 [LID] => s1 [~LID] => s1 [NAV_RESULT] => [DISPLAY_ACTIVE_FROM] => 16 Декабря 2025 [IPROPERTY_VALUES] => Array ( ) [FIELDS] => Array ( [PREVIEW_PICTURE] => Array ( [ID] => 79486 [TIMESTAMP_X] => 16.12.2025 13:20:03 [MODULE_ID] => iblock [HEIGHT] => 733 [WIDTH] => 1100 [FILE_SIZE] => 293188 [CONTENT_TYPE] => image/jpeg [SUBDIR] => iblock/889 [FILE_NAME] => 889ab0bd1491417e8c47100659d10443.jpg [ORIGINAL_NAME] => debris-5590900_960_720.jpg [DESCRIPTION] => [HANDLER_ID] => [EXTERNAL_ID] => 85e93f10811aa9b39866fc2e49ca98aa [~src] => [SRC] => /upload/iblock/889/889ab0bd1491417e8c47100659d10443.jpg [ALT] => Незаконный сброс отходов во время строительства полицейского участка [TITLE] => Незаконный сброс отходов во время строительства полицейского участка ) ) [PROPERTIES] => Array ( [ORIGINAL_URL] => Array ( [ID] => 51 [TIMESTAMP_X] => 2017-10-03 13:37:23 [IBLOCK_ID] => 2 [NAME] => Ссылка на сайте-источнике [ACTIVE] => Y [SORT] => 10 [CODE] => ORIGINAL_URL [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 131020 [VALUE] => /2025/12/16/waste-illegally-dumped-during-construction-of-police-station [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => /2025/12/16/waste-illegally-dumped-during-construction-of-police-station [~DESCRIPTION] => [~NAME] => Ссылка на сайте-источнике [~DEFAULT_VALUE] => ) [THEME_EN] => Array ( [ID] => 280 [TIMESTAMP_X] => 2025-01-08 18:01:42 [IBLOCK_ID] => 2 [NAME] => Тема (en) [ACTIVE] => Y [SORT] => 20 [CODE] => THEME_EN [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => Y [SEARCHABLE] => N [FILTRABLE] => Y [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 131022 [VALUE] => Waste illegally dumped during construction of police station [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => Waste illegally dumped during construction of police station [~DESCRIPTION] => [~NAME] => Тема (en) [~DEFAULT_VALUE] => ) [TEXT_EN] => Array ( [ID] => 281 [TIMESTAMP_X] => 2025-01-08 18:01:42 [IBLOCK_ID] => 2 [NAME] => Текст новости (en) [ACTIVE] => Y [SORT] => 40 [CODE] => TEXT_EN [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => Y [SEARCHABLE] => N [FILTRABLE] => Y [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => HTML [USER_TYPE_SETTINGS] => Array ( [height] => 200 ) [HINT] => [PROPERTY_VALUE_ID] => 131023 [VALUE] => Array ( [TEXT] => Construction waste was illegally dumped while a police station in the Troodos mountain village of Evrychou was being built, according to a report released by the audit office on Tuesday. The report stated that the company contracted to construct the police station had an “initial obligation” to transport most of the waste to a “licenced site”, while also being allowed to “manage at source part of the volume”, and use it “mainly as landfill material”. However, it said, according to information and documents it had received from the public works department, “it clearly emerges that the contractor revised, during the execution stage of the project, the way of managing” the construction waste. “The contractor had the right to reuse the construction waste for backfilling only within the construction site, and not to place it in adjacent areas,” it said. Despite this, however, some of the waste was dumped in an adjacent plot which belongs to the local school board. It stressed that the environment department’s guidelines state that the waste produced “can be used for backfilling … in areas where excavations have been carried out or for engineering reasons in landscape architecture under specific conditions”, but that these conditions were not fulfilled during the construction of the police station. The environment department’s investigation into the matter, it said, found that “from the total balance of quantities of rubble which resulted from the earthmoving work, 6,547 cubic metres remained as the remainder of what had been excavated”. It added that of that quantity, 6,384 cubic metres of waste were dumped in adjacent areas. It said the environment department had found that due to the laying of asphalt at the police station and “the existence of waste there from the past”, there was “difficulty in removing the waste placed before and during the construction” of the police station. As such, it quoted the department as saying, “it is not possible to remove the waste and restore the site”. It added that the environment department had found that the materials dumped were “suitable” to be left where they were, and that the “necessary laboratory tests” had been carried out to prove this, and that for this reason, the department “considers that the removal of construction waste and the restoration of the area is not required”. The audit office then lamented a “significant delay” in the environment department’s decision to investigate the matter, saying that allegations had been “initially raised” as early as January 2022, but that it was not informed by the environment department about the result of any investigation until October 27 this year. It also said that during the construction of the police station, the government’s waste management plan was not followed, and that the amount of waste to be produced was only confirmed after the fact. [TYPE] => HTML ) [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => Array ( [TEXT] => Construction waste was illegally dumped while a police station in the Troodos mountain village of Evrychou was being built, according to a report released by the audit office on Tuesday. The report stated that the company contracted to construct the police station had an “initial obligation” to transport most of the waste to a “licenced site”, while also being allowed to “manage at source part of the volume”, and use it “mainly as landfill material”. However, it said, according to information and documents it had received from the public works department, “it clearly emerges that the contractor revised, during the execution stage of the project, the way of managing” the construction waste. “The contractor had the right to reuse the construction waste for backfilling only within the construction site, and not to place it in adjacent areas,” it said. Despite this, however, some of the waste was dumped in an adjacent plot which belongs to the local school board. It stressed that the environment department’s guidelines state that the waste produced “can be used for backfilling … in areas where excavations have been carried out or for engineering reasons in landscape architecture under specific conditions”, but that these conditions were not fulfilled during the construction of the police station. The environment department’s investigation into the matter, it said, found that “from the total balance of quantities of rubble which resulted from the earthmoving work, 6,547 cubic metres remained as the remainder of what had been excavated”. It added that of that quantity, 6,384 cubic metres of waste were dumped in adjacent areas. It said the environment department had found that due to the laying of asphalt at the police station and “the existence of waste there from the past”, there was “difficulty in removing the waste placed before and during the construction” of the police station. As such, it quoted the department as saying, “it is not possible to remove the waste and restore the site”. It added that the environment department had found that the materials dumped were “suitable” to be left where they were, and that the “necessary laboratory tests” had been carried out to prove this, and that for this reason, the department “considers that the removal of construction waste and the restoration of the area is not required”. The audit office then lamented a “significant delay” in the environment department’s decision to investigate the matter, saying that allegations had been “initially raised” as early as January 2022, but that it was not informed by the environment department about the result of any investigation until October 27 this year. It also said that during the construction of the police station, the government’s waste management plan was not followed, and that the amount of waste to be produced was only confirmed after the fact. [TYPE] => HTML ) [~DESCRIPTION] => [~NAME] => Текст новости (en) [~DEFAULT_VALUE] => ) [FORUM_MESSAGE_CNT] => Array ( [ID] => 2 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Количество комментариев к элементу [ACTIVE] => Y [SORT] => 500 [CODE] => FORUM_MESSAGE_CNT [DEFAULT_VALUE] => [PROPERTY_TYPE] => N [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 63 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Количество комментариев к элементу [~DEFAULT_VALUE] => ) [FORUM_TOPIC_ID] => Array ( [ID] => 3 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Тема форума для комментариев [ACTIVE] => Y [SORT] => 500 [CODE] => FORUM_TOPIC_ID [DEFAULT_VALUE] => [PROPERTY_TYPE] => N [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 62 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Тема форума для комментариев [~DEFAULT_VALUE] => ) [MORE_PHOTO] => Array ( [ID] => 4 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Изображения [ACTIVE] => Y [SORT] => 500 [CODE] => MORE_PHOTO [DEFAULT_VALUE] => [PROPERTY_TYPE] => F [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => Y [XML_ID] => 58 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Изображения [~DEFAULT_VALUE] => ) [PARTMAIN] => Array ( [ID] => 5 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Главная новость раздела [ACTIVE] => Y [SORT] => 500 [CODE] => PARTMAIN [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => C [MULTIPLE] => N [XML_ID] => 56 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [VALUE_ENUM_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Главная новость раздела [~DEFAULT_VALUE] => ) [MAIN] => Array ( [ID] => 6 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Главная новость главной страницы [ACTIVE] => Y [SORT] => 500 [CODE] => MAIN [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => C [MULTIPLE] => N [XML_ID] => 55 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [VALUE_ENUM_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Главная новость главной страницы [~DEFAULT_VALUE] => ) [THEME] => Array ( [ID] => 7 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Тема [ACTIVE] => Y [SORT] => 500 [CODE] => THEME [DEFAULT_VALUE] => [PROPERTY_TYPE] => E [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => Y [XML_ID] => 54 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 1 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => EAutocomplete [USER_TYPE_SETTINGS] => Array ( [VIEW] => A [SHOW_ADD] => Y [MAX_WIDTH] => 250 [MIN_HEIGHT] => 24 [MAX_HEIGHT] => 1000 [BAN_SYM] => ,; [REP_SYM] => [OTHER_REP_SYM] => [IBLOCK_MESS] => Y ) [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Тема [~DEFAULT_VALUE] => ) [LINK_SOURCE] => Array ( [ID] => 8 [TIMESTAMP_X] => 2015-05-25 16:39:08 [IBLOCK_ID] => 2 [NAME] => Источник [ACTIVE] => Y [SORT] => 500 [CODE] => LINK_SOURCE [DEFAULT_VALUE] => russiancyprus [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 53 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 131019 [VALUE] => cyprus-mail.com [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => cyprus-mail.com [~DESCRIPTION] => [~NAME] => Источник [~DEFAULT_VALUE] => russiancyprus ) [IS_SENT_TO_CHANEL] => Array ( [ID] => 167 [TIMESTAMP_X] => 2020-06-25 17:42:19 [IBLOCK_ID] => 2 [NAME] => Is sent to telegram [ACTIVE] => Y [SORT] => 500 [CODE] => IS_SENT_TO_CHANEL [DEFAULT_VALUE] => [PROPERTY_TYPE] => N [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 131034 [VALUE] => 1 [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => 1 [~DESCRIPTION] => [~NAME] => Is sent to telegram [~DEFAULT_VALUE] => ) [YANDEX_TASK_ID_THEME] => Array ( [ID] => 285 [TIMESTAMP_X] => 2025-01-20 21:25:08 [IBLOCK_ID] => 2 [NAME] => YANDEX TASK ID FOR THEME [ACTIVE] => Y [SORT] => 900 [CODE] => YANDEX_TASK_ID_THEME [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 131024 [VALUE] => d7qsjb6ks6c4jguan7o6 [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => d7qsjb6ks6c4jguan7o6 [~DESCRIPTION] => [~NAME] => YANDEX TASK ID FOR THEME [~DEFAULT_VALUE] => ) [YANDEX_TASK_ID] => Array ( [ID] => 284 [TIMESTAMP_X] => 2025-01-20 20:37:32 [IBLOCK_ID] => 2 [NAME] => YANDEX TASK ID [ACTIVE] => Y [SORT] => 1000 [CODE] => YANDEX_TASK_ID [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 131025 [VALUE] => d7q48cm62rqsjt8uptce [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => d7q48cm62rqsjt8uptce [~DESCRIPTION] => [~NAME] => YANDEX TASK ID [~DEFAULT_VALUE] => ) ) [DISPLAY_PROPERTIES] => Array ( ) [IBLOCK] => Array ( [ID] => 2 [~ID] => 2 [TIMESTAMP_X] => 20.01.2025 22:57:06 [~TIMESTAMP_X] => 20.01.2025 22:57:06 [IBLOCK_TYPE_ID] => news [~IBLOCK_TYPE_ID] => news [LID] => s1 [~LID] => s1 [CODE] => infoportal_news_s1 [~CODE] => infoportal_news_s1 [NAME] => Новости [~NAME] => Новости [ACTIVE] => Y [~ACTIVE] => Y [SORT] => 500 [~SORT] => 500 [LIST_PAGE_URL] => /news/ [~LIST_PAGE_URL] => /news/ [DETAIL_PAGE_URL] => #SITE_DIR#/news/#SECTION_CODE#/#CODE#/ [~DETAIL_PAGE_URL] => #SITE_DIR#/news/#SECTION_CODE#/#CODE#/ [SECTION_PAGE_URL] => #SITE_DIR#/news/#CODE#/ [~SECTION_PAGE_URL] => #SITE_DIR#/news/#CODE#/ [PICTURE] => [~PICTURE] => [DESCRIPTION] => [~DESCRIPTION] => [DESCRIPTION_TYPE] => text [~DESCRIPTION_TYPE] => text [RSS_TTL] => 24 [~RSS_TTL] => 24 [RSS_ACTIVE] => Y [~RSS_ACTIVE] => Y [RSS_FILE_ACTIVE] => N [~RSS_FILE_ACTIVE] => N [RSS_FILE_LIMIT] => 0 [~RSS_FILE_LIMIT] => 0 [RSS_FILE_DAYS] => 0 [~RSS_FILE_DAYS] => 0 [RSS_YANDEX_ACTIVE] => N [~RSS_YANDEX_ACTIVE] => N [XML_ID] => infoportal_news_s1 [~XML_ID] => infoportal_news_s1 [TMP_ID] => adf9113ce97738184efe133d53e3d656 [~TMP_ID] => adf9113ce97738184efe133d53e3d656 [INDEX_ELEMENT] => Y [~INDEX_ELEMENT] => Y [INDEX_SECTION] => N [~INDEX_SECTION] => N [WORKFLOW] => N [~WORKFLOW] => N [BIZPROC] => N [~BIZPROC] => N [SECTION_CHOOSER] => L [~SECTION_CHOOSER] => L [LIST_MODE] => [~LIST_MODE] => [RIGHTS_MODE] => S [~RIGHTS_MODE] => S [SECTION_PROPERTY] => [~SECTION_PROPERTY] => [PROPERTY_INDEX] => [~PROPERTY_INDEX] => [VERSION] => 1 [~VERSION] => 1 [LAST_CONV_ELEMENT] => 0 [~LAST_CONV_ELEMENT] => 0 [SOCNET_GROUP_ID] => [~SOCNET_GROUP_ID] => [EDIT_FILE_BEFORE] => [~EDIT_FILE_BEFORE] => [EDIT_FILE_AFTER] => [~EDIT_FILE_AFTER] => [SECTIONS_NAME] => Разделы [~SECTIONS_NAME] => Разделы [SECTION_NAME] => Раздел [~SECTION_NAME] => Раздел [ELEMENTS_NAME] => Новости [~ELEMENTS_NAME] => Новости [ELEMENT_NAME] => Новость [~ELEMENT_NAME] => Новость [EXTERNAL_ID] => infoportal_news_s1 [~EXTERNAL_ID] => infoportal_news_s1 [LANG_DIR] => / [~LANG_DIR] => / [SERVER_NAME] => russiancyprus.news [~SERVER_NAME] => russiancyprus.news ) [SECTION] => Array ( [PATH] => Array ( [0] => Array ( [ID] => 2 [~ID] => 2 [TIMESTAMP_X] => 2025-01-20 22:54:27 [~TIMESTAMP_X] => 2025-01-20 22:54:27 [MODIFIED_BY] => 1 [~MODIFIED_BY] => 1 [DATE_CREATE] => 2015-04-24 10:15:32 [~DATE_CREATE] => 2015-04-24 10:15:32 [CREATED_BY] => 1 [~CREATED_BY] => 1 [IBLOCK_ID] => 2 [~IBLOCK_ID] => 2 [IBLOCK_SECTION_ID] => [~IBLOCK_SECTION_ID] => [ACTIVE] => Y [~ACTIVE] => Y [GLOBAL_ACTIVE] => Y [~GLOBAL_ACTIVE] => Y [SORT] => 5 [~SORT] => 5 [NAME] => Общество и политика [~NAME] => Общество и политика [PICTURE] => [~PICTURE] => [LEFT_MARGIN] => 1 [~LEFT_MARGIN] => 1 [RIGHT_MARGIN] => 2 [~RIGHT_MARGIN] => 2 [DEPTH_LEVEL] => 1 [~DEPTH_LEVEL] => 1 [DESCRIPTION] => [~DESCRIPTION] => [DESCRIPTION_TYPE] => text [~DESCRIPTION_TYPE] => text [SEARCHABLE_CONTENT] => Общество и политика [~SEARCHABLE_CONTENT] => Общество и политика [CODE] => society [~CODE] => society [XML_ID] => 111 [~XML_ID] => 111 [TMP_ID] => [~TMP_ID] => [DETAIL_PICTURE] => [~DETAIL_PICTURE] => [SOCNET_GROUP_ID] => [~SOCNET_GROUP_ID] => [LIST_PAGE_URL] => /news/ [~LIST_PAGE_URL] => /news/ [SECTION_PAGE_URL] => /news/society/ [~SECTION_PAGE_URL] => /news/society/ [IBLOCK_TYPE_ID] => news [~IBLOCK_TYPE_ID] => news [IBLOCK_CODE] => infoportal_news_s1 [~IBLOCK_CODE] => infoportal_news_s1 [IBLOCK_EXTERNAL_ID] => infoportal_news_s1 [~IBLOCK_EXTERNAL_ID] => infoportal_news_s1 [EXTERNAL_ID] => 111 [~EXTERNAL_ID] => 111 [IPROPERTY_VALUES] => Array ( ) ) ) ) [SECTION_URL] => /news/society/ [ITEMS_THEME] => Array ( ) )
Незаконный сброс отходов во время строительства полицейского участка
Согласно отчёту, опубликованному во вторник аудиторской службой, строительный мусор был незаконно выброшен во время строительства полицейского участка в горной деревне Эвриху в Троодосе.

В отчёте говорится, что компания, заключившая контракт на строительство полицейского участка, имела «первоначальное обязательство» перевозить большую часть отходов на «лицензированный объект», при этом ей было разрешено «управлять частью объёма отходов у источника» и использовать их «в основном в качестве материала для свалок».

Однако, согласно отчёту, согласно информации и документам, полученным из департамента общественных работ, «ясно видно, что подрядчик пересмотрел способ управления» строительными отходами на этапе выполнения проекта.

«Подрядчик имел право повторно использовать строительный мусор для засыпки только в пределах строительной площадки и не размещать его на прилегающих территориях», — говорится в отчёте.

Несмотря на это, часть отходов была выброшена на прилегающем участке, который принадлежит местному школьному совету.

В отчёте подчёркивается, что в соответствии с инструкциями департамента окружающей среды, произведённые отходы «могут быть использованы для засыпки… в местах, где проводились раскопки, или по инженерным причинам в ландшафтной архитектуре при определённых условиях», но эти условия не были выполнены при строительстве полицейского участка.

Расследование департамента окружающей среды показало, что «из общего объёма количества щебня, образовавшегося в результате земляных работ, 6 547 кубических метров остались в качестве остатка того, что было раскопано».

Кроме того, из этого количества 6 384 кубических метра отходов были выброшены на прилегающие территории.

В отчёте говорится, что департамент окружающей среды установил: из-за укладки асфальта на территории полицейского участка и «наличия там отходов с прошлого» возникла «трудность в вывозе отходов, размещённых до и во время строительства» полицейского участка.

Таким образом, по словам ведомства, «вывезти отходы и восстановить территорию невозможно».

Кроме того, в отчёте указано, что департамент окружающей среды установил: выброшенные материалы «подходят» для того, чтобы их оставили на месте, и что для доказательства этого были проведены «необходимые лабораторные испытания», и по этой причине департамент «считает, что вывоз строительного мусора и восстановление территории не требуется».

Затем аудиторская служба выразила сожаление по поводу «значительной задержки» в принятии департаментом окружающей среды решения о расследовании этого вопроса, заявив, что обвинения были «первоначально выдвинуты» ещё в январе 2022 года, но департамент окружающей среды не сообщил о результатах расследования до 27 октября этого года.

Также в отчёте говорится, что во время строительства полицейского участка план правительства по обращению с отходами не соблюдался, и объём образующихся отходов был подтверждён только постфактум.

Материал подготовлен с использованием издания Cyprus-mail.com с обработкой ИИ.