Депутаты парламента указывают на значительные задержки в реализации проекта нового музея в Никосии 9 Октября 2025
Array ( [PREVIEW_PICTURE] => Array ( [ID] => 76727 [TIMESTAMP_X] => 09.10.2025 17:50:04 [MODULE_ID] => iblock [HEIGHT] => 733 [WIDTH] => 1100 [FILE_SIZE] => 195772 [CONTENT_TYPE] => image/jpeg [SUBDIR] => iblock/257 [FILE_NAME] => 257e230b01091ea3c4550d4320bf5b48.jpg [ORIGINAL_NAME] => museum-1.jpg [DESCRIPTION] => [HANDLER_ID] => [EXTERNAL_ID] => b4640b4849beff1a5eaa4bb87e939bb5 [~src] => [SRC] => /upload/iblock/257/257e230b01091ea3c4550d4320bf5b48.jpg [ALT] => Депутаты парламента указывают на значительные задержки в реализации проекта нового музея в Никосии [TITLE] => Депутаты парламента указывают на значительные задержки в реализации проекта нового музея в Никосии ) [~PREVIEW_PICTURE] => 76727 [ID] => 38918 [~ID] => 38918 [NAME] => Депутаты парламента указывают на значительные задержки в реализации проекта нового музея в Никосии [~NAME] => Депутаты парламента указывают на значительные задержки в реализации проекта нового музея в Никосии [IBLOCK_ID] => 2 [~IBLOCK_ID] => 2 [IBLOCK_SECTION_ID] => 2 [~IBLOCK_SECTION_ID] => 2 [DETAIL_TEXT] => В четверг депутаты задавали вопросы о просьбе подрядчика предоставить дополнительные 500 дней для завершения строительства нового археологического музея в Никосии, поскольку сроки завершения к июлю 2026 года теперь кажутся недостижимыми.

Контракт на строительство музея получила компания Cyfield.

В транспортном комитете Палаты представители правительства подтвердили, что с начала работ подрядчик подал около 20 запросов, которые в сумме могут добавить ещё 500 дней для завершения проекта.

Некоторые запросы обоснованы, другие — нет, сообщил депутатам представитель департамента общественных работ.

Задержки связаны с несколькими факторами, такими как жара, забастовки бетонщиков и внесение изменений в первоначальный проект.

Правительство рассмотрит запросы подрядчика в начале следующего года и решит, предоставлять ли продление.

Ева Иордану из департамента общественных работ назвала проект «чрезвычайно сложным», который столкнулся с «беспрецедентными ситуациями» — например, необходимостью осушения соседней реки, сложностями с земляными работами и необходимостью построить дополнительную конструкцию.

Она напомнила, что закладка первого камня в фундамент нового музея состоялась в январе 2023 года, а дата завершения была назначена на 9 июля 2026 года.

Что касается стоимости — 144 миллиона евро — Иордану сообщила, что подрядчик пока не требовал дополнительных денег.

Со своей стороны, Гиоргос Хрисохус, представляющий Cyfield, настаивал на том, что проект идёт по графику.

«Первоначальный срок завершения с самого начала был нереалистичным, поскольку сам проект — это произведение искусства», — прокомментировал он.

Представитель Научно-технической палаты (Etek) говорил о «вызывающей тревогу задержке», отметив, что на данный момент израсходовано только 30 миллионов евро из первоначального бюджета — это показывает, насколько проект отстаёт.

Депутат от партии Dipa Мариноса Мушутас попросил разъяснить, «какой процент бюджета предполагалось освоить за 35 месяцев, на что мы вышли сегодня».

Депутат от Акел Костис Коста сказал, что некоторые из причин задержек звучат неубедительно.

«Мы с самого начала знали, что там есть река, это не было чем-то неизвестным».

Музей общей площадью 30 000 квадратных метров (включая подвалы) будет построен на участке площадью 40 000 квадратных метров на месте старой больницы.

В нём будут представлены постоянные выставочные площади площадью 5 500 квадратных метров, где разместится около 6 500 предметов старины; временные выставочные площади — 1 000 квадратных метров; реставрационные мастерские — 2 000 квадратных метров; подземные парковочные места; хранилище древностей — 5 000 квадратных метров; ресторан, кафе, библиотека, амфитеатр, офисы, художественный магазин и обширное благоустройство внешних пространств. [~DETAIL_TEXT] => В четверг депутаты задавали вопросы о просьбе подрядчика предоставить дополнительные 500 дней для завершения строительства нового археологического музея в Никосии, поскольку сроки завершения к июлю 2026 года теперь кажутся недостижимыми.

Контракт на строительство музея получила компания Cyfield.

В транспортном комитете Палаты представители правительства подтвердили, что с начала работ подрядчик подал около 20 запросов, которые в сумме могут добавить ещё 500 дней для завершения проекта.

Некоторые запросы обоснованы, другие — нет, сообщил депутатам представитель департамента общественных работ.

Задержки связаны с несколькими факторами, такими как жара, забастовки бетонщиков и внесение изменений в первоначальный проект.

Правительство рассмотрит запросы подрядчика в начале следующего года и решит, предоставлять ли продление.

Ева Иордану из департамента общественных работ назвала проект «чрезвычайно сложным», который столкнулся с «беспрецедентными ситуациями» — например, необходимостью осушения соседней реки, сложностями с земляными работами и необходимостью построить дополнительную конструкцию.

Она напомнила, что закладка первого камня в фундамент нового музея состоялась в январе 2023 года, а дата завершения была назначена на 9 июля 2026 года.

Что касается стоимости — 144 миллиона евро — Иордану сообщила, что подрядчик пока не требовал дополнительных денег.

Со своей стороны, Гиоргос Хрисохус, представляющий Cyfield, настаивал на том, что проект идёт по графику.

«Первоначальный срок завершения с самого начала был нереалистичным, поскольку сам проект — это произведение искусства», — прокомментировал он.

Представитель Научно-технической палаты (Etek) говорил о «вызывающей тревогу задержке», отметив, что на данный момент израсходовано только 30 миллионов евро из первоначального бюджета — это показывает, насколько проект отстаёт.

Депутат от партии Dipa Мариноса Мушутас попросил разъяснить, «какой процент бюджета предполагалось освоить за 35 месяцев, на что мы вышли сегодня».

Депутат от Акел Костис Коста сказал, что некоторые из причин задержек звучат неубедительно.

«Мы с самого начала знали, что там есть река, это не было чем-то неизвестным».

Музей общей площадью 30 000 квадратных метров (включая подвалы) будет построен на участке площадью 40 000 квадратных метров на месте старой больницы.

В нём будут представлены постоянные выставочные площади площадью 5 500 квадратных метров, где разместится около 6 500 предметов старины; временные выставочные площади — 1 000 квадратных метров; реставрационные мастерские — 2 000 квадратных метров; подземные парковочные места; хранилище древностей — 5 000 квадратных метров; ресторан, кафе, библиотека, амфитеатр, офисы, художественный магазин и обширное благоустройство внешних пространств. [DETAIL_TEXT_TYPE] => html [~DETAIL_TEXT_TYPE] => html [PREVIEW_TEXT] => В четверг депутаты задавали вопросы о просьбе подрядчика предоставить дополнительные... [~PREVIEW_TEXT] => В четверг депутаты задавали вопросы о просьбе подрядчика предоставить дополнительные... [PREVIEW_TEXT_TYPE] => html [~PREVIEW_TEXT_TYPE] => html [DETAIL_PICTURE] => Array ( [SRC] => /upload/resize_cache/iblock/257/600_400_1/257e230b01091ea3c4550d4320bf5b48.jpg [WIDTH] => 600 [HEIGHT] => 399 ) [~DETAIL_PICTURE] => 76728 [ACTIVE_FROM] => 09.10.2025 17:50:00 [~ACTIVE_FROM] => 09.10.2025 17:50:00 [LIST_PAGE_URL] => /news/ [~LIST_PAGE_URL] => /news/ [DETAIL_PAGE_URL] => /news/society/mps-flag-major-delays-to-new-nicosia-museum-project/ [~DETAIL_PAGE_URL] => /news/society/mps-flag-major-delays-to-new-nicosia-museum-project/ [LANG_DIR] => / [~LANG_DIR] => / [CODE] => mps-flag-major-delays-to-new-nicosia-museum-project [~CODE] => mps-flag-major-delays-to-new-nicosia-museum-project [EXTERNAL_ID] => 38918 [~EXTERNAL_ID] => 38918 [IBLOCK_TYPE_ID] => news [~IBLOCK_TYPE_ID] => news [IBLOCK_CODE] => infoportal_news_s1 [~IBLOCK_CODE] => infoportal_news_s1 [IBLOCK_EXTERNAL_ID] => infoportal_news_s1 [~IBLOCK_EXTERNAL_ID] => infoportal_news_s1 [LID] => s1 [~LID] => s1 [NAV_RESULT] => [DISPLAY_ACTIVE_FROM] => 9 Октября 2025 [IPROPERTY_VALUES] => Array ( ) [FIELDS] => Array ( [PREVIEW_PICTURE] => Array ( [ID] => 76727 [TIMESTAMP_X] => 09.10.2025 17:50:04 [MODULE_ID] => iblock [HEIGHT] => 733 [WIDTH] => 1100 [FILE_SIZE] => 195772 [CONTENT_TYPE] => image/jpeg [SUBDIR] => iblock/257 [FILE_NAME] => 257e230b01091ea3c4550d4320bf5b48.jpg [ORIGINAL_NAME] => museum-1.jpg [DESCRIPTION] => [HANDLER_ID] => [EXTERNAL_ID] => b4640b4849beff1a5eaa4bb87e939bb5 [~src] => [SRC] => /upload/iblock/257/257e230b01091ea3c4550d4320bf5b48.jpg [ALT] => Депутаты парламента указывают на значительные задержки в реализации проекта нового музея в Никосии [TITLE] => Депутаты парламента указывают на значительные задержки в реализации проекта нового музея в Никосии ) ) [PROPERTIES] => Array ( [ORIGINAL_URL] => Array ( [ID] => 51 [TIMESTAMP_X] => 2017-10-03 13:37:23 [IBLOCK_ID] => 2 [NAME] => Ссылка на сайте-источнике [ACTIVE] => Y [SORT] => 10 [CODE] => ORIGINAL_URL [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 119859 [VALUE] => /2025/10/09/mps-flag-major-delays-to-new-nicosia-museum-project [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => /2025/10/09/mps-flag-major-delays-to-new-nicosia-museum-project [~DESCRIPTION] => [~NAME] => Ссылка на сайте-источнике [~DEFAULT_VALUE] => ) [THEME_EN] => Array ( [ID] => 280 [TIMESTAMP_X] => 2025-01-08 18:01:42 [IBLOCK_ID] => 2 [NAME] => Тема (en) [ACTIVE] => Y [SORT] => 20 [CODE] => THEME_EN [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => Y [SEARCHABLE] => N [FILTRABLE] => Y [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 119861 [VALUE] => MPs flag major delays to new Nicosia museum project [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => MPs flag major delays to new Nicosia museum project [~DESCRIPTION] => [~NAME] => Тема (en) [~DEFAULT_VALUE] => ) [TEXT_EN] => Array ( [ID] => 281 [TIMESTAMP_X] => 2025-01-08 18:01:42 [IBLOCK_ID] => 2 [NAME] => Текст новости (en) [ACTIVE] => Y [SORT] => 40 [CODE] => TEXT_EN [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => Y [SEARCHABLE] => N [FILTRABLE] => Y [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => HTML [USER_TYPE_SETTINGS] => Array ( [height] => 200 ) [HINT] => [PROPERTY_VALUE_ID] => 119862 [VALUE] => Array ( [TEXT] => MPs on Thursday asked questions about the contractor’s request for 500 extra days to finish the new archaeological museum in Nicosia, with the July 2026 timetable for completion now looking unattainable. The company awarded the museum construction contract is Cyfield. At the House transport committee, government officials confirmed that the contractor has submitted about 20 requests since starting work, which together would amount to an additional 500 days to finish the project. Some of the requests are justified, others not, an official with the department of public works told MPs. The delays are attributed to several factors, like heatwaves, strikes by concrete workers and amendments to the original designs. The government will review the contractor’s requests at the start of the next year and decide then whether to grant an extension. Eva Iordanous, of the department of public works, called it “an extremely difficult project” that faced “unprecedented situations” – such as having to drain the adjacent river, complications with earthworks, and the need to build an additional structure. She recalled that the foundation stone for the new museum was laid in January 2023, with the completion date set for July 9, 2026. Regarding the cost – €144 million – Iordanous said the contractor has so far not demanded more money. For his part, Giorgos Chrysochoos, representing Cyfield, insisted that the project remains on schedule. “The initial deadline for completion was not realistic from the outset, as the project itself is a work of art,” he commented. An official of the Scientific and Technical Chamber (Etek) spoke of “an alarming delay”, pointing out that just €30 million of the initial budget has been spent to date – showing how far behind the project is. Marinos Moushiouttas, an MP with the Dipa party, asked for clarifications as to “what percentage of the budget had been expected to be absorbed within 35 months, which is where we are today”. Akel MP Costas Costa said some of the reasons cited for the delays ring hollow. “We knew from the beginning that there was a river there, it was not something unknown.” The museum, with a total area of 30,000 square metres (including the basements), will be erected on a 40,000 square metre plot at the site of the old hospital. It will include permanent exhibition spaces of 5,500 square metres hosting around 6,500 antiquities; temporary exhibition spaces of 1,000 square metres; conservation workshops of 2,000 square metres; underground parking spaces; antiquities storage of 5,000 square metres; a restaurant, café, library, amphitheatre, offices, an art shop and extensive landscaping of external spaces. [TYPE] => HTML ) [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => Array ( [TEXT] => MPs on Thursday asked questions about the contractor’s request for 500 extra days to finish the new archaeological museum in Nicosia, with the July 2026 timetable for completion now looking unattainable. The company awarded the museum construction contract is Cyfield. At the House transport committee, government officials confirmed that the contractor has submitted about 20 requests since starting work, which together would amount to an additional 500 days to finish the project. Some of the requests are justified, others not, an official with the department of public works told MPs. The delays are attributed to several factors, like heatwaves, strikes by concrete workers and amendments to the original designs. The government will review the contractor’s requests at the start of the next year and decide then whether to grant an extension. Eva Iordanous, of the department of public works, called it “an extremely difficult project” that faced “unprecedented situations” – such as having to drain the adjacent river, complications with earthworks, and the need to build an additional structure. She recalled that the foundation stone for the new museum was laid in January 2023, with the completion date set for July 9, 2026. Regarding the cost – €144 million – Iordanous said the contractor has so far not demanded more money. For his part, Giorgos Chrysochoos, representing Cyfield, insisted that the project remains on schedule. “The initial deadline for completion was not realistic from the outset, as the project itself is a work of art,” he commented. An official of the Scientific and Technical Chamber (Etek) spoke of “an alarming delay”, pointing out that just €30 million of the initial budget has been spent to date – showing how far behind the project is. Marinos Moushiouttas, an MP with the Dipa party, asked for clarifications as to “what percentage of the budget had been expected to be absorbed within 35 months, which is where we are today”. Akel MP Costas Costa said some of the reasons cited for the delays ring hollow. “We knew from the beginning that there was a river there, it was not something unknown.” The museum, with a total area of 30,000 square metres (including the basements), will be erected on a 40,000 square metre plot at the site of the old hospital. It will include permanent exhibition spaces of 5,500 square metres hosting around 6,500 antiquities; temporary exhibition spaces of 1,000 square metres; conservation workshops of 2,000 square metres; underground parking spaces; antiquities storage of 5,000 square metres; a restaurant, café, library, amphitheatre, offices, an art shop and extensive landscaping of external spaces. [TYPE] => HTML ) [~DESCRIPTION] => [~NAME] => Текст новости (en) [~DEFAULT_VALUE] => ) [FORUM_MESSAGE_CNT] => Array ( [ID] => 2 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Количество комментариев к элементу [ACTIVE] => Y [SORT] => 500 [CODE] => FORUM_MESSAGE_CNT [DEFAULT_VALUE] => [PROPERTY_TYPE] => N [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 63 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Количество комментариев к элементу [~DEFAULT_VALUE] => ) [FORUM_TOPIC_ID] => Array ( [ID] => 3 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Тема форума для комментариев [ACTIVE] => Y [SORT] => 500 [CODE] => FORUM_TOPIC_ID [DEFAULT_VALUE] => [PROPERTY_TYPE] => N [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 62 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Тема форума для комментариев [~DEFAULT_VALUE] => ) [MORE_PHOTO] => Array ( [ID] => 4 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Изображения [ACTIVE] => Y [SORT] => 500 [CODE] => MORE_PHOTO [DEFAULT_VALUE] => [PROPERTY_TYPE] => F [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => Y [XML_ID] => 58 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Изображения [~DEFAULT_VALUE] => ) [PARTMAIN] => Array ( [ID] => 5 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Главная новость раздела [ACTIVE] => Y [SORT] => 500 [CODE] => PARTMAIN [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => C [MULTIPLE] => N [XML_ID] => 56 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [VALUE_ENUM_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Главная новость раздела [~DEFAULT_VALUE] => ) [MAIN] => Array ( [ID] => 6 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Главная новость главной страницы [ACTIVE] => Y [SORT] => 500 [CODE] => MAIN [DEFAULT_VALUE] => [PROPERTY_TYPE] => L [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => C [MULTIPLE] => N [XML_ID] => 55 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [VALUE_ENUM_ID] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Главная новость главной страницы [~DEFAULT_VALUE] => ) [THEME] => Array ( [ID] => 7 [TIMESTAMP_X] => 2015-04-24 10:27:06 [IBLOCK_ID] => 2 [NAME] => Тема [ACTIVE] => Y [SORT] => 500 [CODE] => THEME [DEFAULT_VALUE] => [PROPERTY_TYPE] => E [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => Y [XML_ID] => 54 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 1 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => EAutocomplete [USER_TYPE_SETTINGS] => Array ( [VIEW] => A [SHOW_ADD] => Y [MAX_WIDTH] => 250 [MIN_HEIGHT] => 24 [MAX_HEIGHT] => 1000 [BAN_SYM] => ,; [REP_SYM] => [OTHER_REP_SYM] => [IBLOCK_MESS] => Y ) [HINT] => [PROPERTY_VALUE_ID] => [VALUE] => [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => [~DESCRIPTION] => [~NAME] => Тема [~DEFAULT_VALUE] => ) [LINK_SOURCE] => Array ( [ID] => 8 [TIMESTAMP_X] => 2015-05-25 16:39:08 [IBLOCK_ID] => 2 [NAME] => Источник [ACTIVE] => Y [SORT] => 500 [CODE] => LINK_SOURCE [DEFAULT_VALUE] => russiancyprus [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => 53 [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 119858 [VALUE] => cyprus-mail.com [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => cyprus-mail.com [~DESCRIPTION] => [~NAME] => Источник [~DEFAULT_VALUE] => russiancyprus ) [IS_SENT_TO_CHANEL] => Array ( [ID] => 167 [TIMESTAMP_X] => 2020-06-25 17:42:19 [IBLOCK_ID] => 2 [NAME] => Is sent to telegram [ACTIVE] => Y [SORT] => 500 [CODE] => IS_SENT_TO_CHANEL [DEFAULT_VALUE] => [PROPERTY_TYPE] => N [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 119865 [VALUE] => 1 [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => 1 [~DESCRIPTION] => [~NAME] => Is sent to telegram [~DEFAULT_VALUE] => ) [YANDEX_TASK_ID_THEME] => Array ( [ID] => 285 [TIMESTAMP_X] => 2025-01-20 21:25:08 [IBLOCK_ID] => 2 [NAME] => YANDEX TASK ID FOR THEME [ACTIVE] => Y [SORT] => 900 [CODE] => YANDEX_TASK_ID_THEME [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 119863 [VALUE] => d7q1ltaejc9h3328c1j6 [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => d7q1ltaejc9h3328c1j6 [~DESCRIPTION] => [~NAME] => YANDEX TASK ID FOR THEME [~DEFAULT_VALUE] => ) [YANDEX_TASK_ID] => Array ( [ID] => 284 [TIMESTAMP_X] => 2025-01-20 20:37:32 [IBLOCK_ID] => 2 [NAME] => YANDEX TASK ID [ACTIVE] => Y [SORT] => 1000 [CODE] => YANDEX_TASK_ID [DEFAULT_VALUE] => [PROPERTY_TYPE] => S [ROW_COUNT] => 1 [COL_COUNT] => 30 [LIST_TYPE] => L [MULTIPLE] => N [XML_ID] => [FILE_TYPE] => [MULTIPLE_CNT] => 5 [TMP_ID] => [LINK_IBLOCK_ID] => 0 [WITH_DESCRIPTION] => N [SEARCHABLE] => N [FILTRABLE] => N [IS_REQUIRED] => N [VERSION] => 1 [USER_TYPE] => [USER_TYPE_SETTINGS] => [HINT] => [PROPERTY_VALUE_ID] => 119864 [VALUE] => d7qoeh4dm3pflu98edaa [DESCRIPTION] => [VALUE_ENUM] => [VALUE_XML_ID] => [VALUE_SORT] => [~VALUE] => d7qoeh4dm3pflu98edaa [~DESCRIPTION] => [~NAME] => YANDEX TASK ID [~DEFAULT_VALUE] => ) ) [DISPLAY_PROPERTIES] => Array ( ) [IBLOCK] => Array ( [ID] => 2 [~ID] => 2 [TIMESTAMP_X] => 20.01.2025 22:57:06 [~TIMESTAMP_X] => 20.01.2025 22:57:06 [IBLOCK_TYPE_ID] => news [~IBLOCK_TYPE_ID] => news [LID] => s1 [~LID] => s1 [CODE] => infoportal_news_s1 [~CODE] => infoportal_news_s1 [NAME] => Новости [~NAME] => Новости [ACTIVE] => Y [~ACTIVE] => Y [SORT] => 500 [~SORT] => 500 [LIST_PAGE_URL] => /news/ [~LIST_PAGE_URL] => /news/ [DETAIL_PAGE_URL] => #SITE_DIR#/news/#SECTION_CODE#/#CODE#/ [~DETAIL_PAGE_URL] => #SITE_DIR#/news/#SECTION_CODE#/#CODE#/ [SECTION_PAGE_URL] => #SITE_DIR#/news/#CODE#/ [~SECTION_PAGE_URL] => #SITE_DIR#/news/#CODE#/ [PICTURE] => [~PICTURE] => [DESCRIPTION] => [~DESCRIPTION] => [DESCRIPTION_TYPE] => text [~DESCRIPTION_TYPE] => text [RSS_TTL] => 24 [~RSS_TTL] => 24 [RSS_ACTIVE] => Y [~RSS_ACTIVE] => Y [RSS_FILE_ACTIVE] => N [~RSS_FILE_ACTIVE] => N [RSS_FILE_LIMIT] => 0 [~RSS_FILE_LIMIT] => 0 [RSS_FILE_DAYS] => 0 [~RSS_FILE_DAYS] => 0 [RSS_YANDEX_ACTIVE] => N [~RSS_YANDEX_ACTIVE] => N [XML_ID] => infoportal_news_s1 [~XML_ID] => infoportal_news_s1 [TMP_ID] => adf9113ce97738184efe133d53e3d656 [~TMP_ID] => adf9113ce97738184efe133d53e3d656 [INDEX_ELEMENT] => Y [~INDEX_ELEMENT] => Y [INDEX_SECTION] => N [~INDEX_SECTION] => N [WORKFLOW] => N [~WORKFLOW] => N [BIZPROC] => N [~BIZPROC] => N [SECTION_CHOOSER] => L [~SECTION_CHOOSER] => L [LIST_MODE] => [~LIST_MODE] => [RIGHTS_MODE] => S [~RIGHTS_MODE] => S [SECTION_PROPERTY] => [~SECTION_PROPERTY] => [PROPERTY_INDEX] => [~PROPERTY_INDEX] => [VERSION] => 1 [~VERSION] => 1 [LAST_CONV_ELEMENT] => 0 [~LAST_CONV_ELEMENT] => 0 [SOCNET_GROUP_ID] => [~SOCNET_GROUP_ID] => [EDIT_FILE_BEFORE] => [~EDIT_FILE_BEFORE] => [EDIT_FILE_AFTER] => [~EDIT_FILE_AFTER] => [SECTIONS_NAME] => Разделы [~SECTIONS_NAME] => Разделы [SECTION_NAME] => Раздел [~SECTION_NAME] => Раздел [ELEMENTS_NAME] => Новости [~ELEMENTS_NAME] => Новости [ELEMENT_NAME] => Новость [~ELEMENT_NAME] => Новость [EXTERNAL_ID] => infoportal_news_s1 [~EXTERNAL_ID] => infoportal_news_s1 [LANG_DIR] => / [~LANG_DIR] => / [SERVER_NAME] => russiancyprus.news [~SERVER_NAME] => russiancyprus.news ) [SECTION] => Array ( [PATH] => Array ( [0] => Array ( [ID] => 2 [~ID] => 2 [TIMESTAMP_X] => 2025-01-20 22:54:27 [~TIMESTAMP_X] => 2025-01-20 22:54:27 [MODIFIED_BY] => 1 [~MODIFIED_BY] => 1 [DATE_CREATE] => 2015-04-24 10:15:32 [~DATE_CREATE] => 2015-04-24 10:15:32 [CREATED_BY] => 1 [~CREATED_BY] => 1 [IBLOCK_ID] => 2 [~IBLOCK_ID] => 2 [IBLOCK_SECTION_ID] => [~IBLOCK_SECTION_ID] => [ACTIVE] => Y [~ACTIVE] => Y [GLOBAL_ACTIVE] => Y [~GLOBAL_ACTIVE] => Y [SORT] => 5 [~SORT] => 5 [NAME] => Общество и политика [~NAME] => Общество и политика [PICTURE] => [~PICTURE] => [LEFT_MARGIN] => 1 [~LEFT_MARGIN] => 1 [RIGHT_MARGIN] => 2 [~RIGHT_MARGIN] => 2 [DEPTH_LEVEL] => 1 [~DEPTH_LEVEL] => 1 [DESCRIPTION] => [~DESCRIPTION] => [DESCRIPTION_TYPE] => text [~DESCRIPTION_TYPE] => text [SEARCHABLE_CONTENT] => Общество и политика [~SEARCHABLE_CONTENT] => Общество и политика [CODE] => society [~CODE] => society [XML_ID] => 111 [~XML_ID] => 111 [TMP_ID] => [~TMP_ID] => [DETAIL_PICTURE] => [~DETAIL_PICTURE] => [SOCNET_GROUP_ID] => [~SOCNET_GROUP_ID] => [LIST_PAGE_URL] => /news/ [~LIST_PAGE_URL] => /news/ [SECTION_PAGE_URL] => /news/society/ [~SECTION_PAGE_URL] => /news/society/ [IBLOCK_TYPE_ID] => news [~IBLOCK_TYPE_ID] => news [IBLOCK_CODE] => infoportal_news_s1 [~IBLOCK_CODE] => infoportal_news_s1 [IBLOCK_EXTERNAL_ID] => infoportal_news_s1 [~IBLOCK_EXTERNAL_ID] => infoportal_news_s1 [EXTERNAL_ID] => 111 [~EXTERNAL_ID] => 111 [IPROPERTY_VALUES] => Array ( ) ) ) ) [SECTION_URL] => /news/society/ [ITEMS_THEME] => Array ( ) )
Депутаты парламента указывают на значительные задержки в реализации проекта нового музея в Никосии
В четверг депутаты задавали вопросы о просьбе подрядчика предоставить дополнительные 500 дней для завершения строительства нового археологического музея в Никосии, поскольку сроки завершения к июлю 2026 года теперь кажутся недостижимыми.

Контракт на строительство музея получила компания Cyfield.

В транспортном комитете Палаты представители правительства подтвердили, что с начала работ подрядчик подал около 20 запросов, которые в сумме могут добавить ещё 500 дней для завершения проекта.

Некоторые запросы обоснованы, другие — нет, сообщил депутатам представитель департамента общественных работ.

Задержки связаны с несколькими факторами, такими как жара, забастовки бетонщиков и внесение изменений в первоначальный проект.

Правительство рассмотрит запросы подрядчика в начале следующего года и решит, предоставлять ли продление.

Ева Иордану из департамента общественных работ назвала проект «чрезвычайно сложным», который столкнулся с «беспрецедентными ситуациями» — например, необходимостью осушения соседней реки, сложностями с земляными работами и необходимостью построить дополнительную конструкцию.

Она напомнила, что закладка первого камня в фундамент нового музея состоялась в январе 2023 года, а дата завершения была назначена на 9 июля 2026 года.

Что касается стоимости — 144 миллиона евро — Иордану сообщила, что подрядчик пока не требовал дополнительных денег.

Со своей стороны, Гиоргос Хрисохус, представляющий Cyfield, настаивал на том, что проект идёт по графику.

«Первоначальный срок завершения с самого начала был нереалистичным, поскольку сам проект — это произведение искусства», — прокомментировал он.

Представитель Научно-технической палаты (Etek) говорил о «вызывающей тревогу задержке», отметив, что на данный момент израсходовано только 30 миллионов евро из первоначального бюджета — это показывает, насколько проект отстаёт.

Депутат от партии Dipa Мариноса Мушутас попросил разъяснить, «какой процент бюджета предполагалось освоить за 35 месяцев, на что мы вышли сегодня».

Депутат от Акел Костис Коста сказал, что некоторые из причин задержек звучат неубедительно.

«Мы с самого начала знали, что там есть река, это не было чем-то неизвестным».

Музей общей площадью 30 000 квадратных метров (включая подвалы) будет построен на участке площадью 40 000 квадратных метров на месте старой больницы.

В нём будут представлены постоянные выставочные площади площадью 5 500 квадратных метров, где разместится около 6 500 предметов старины; временные выставочные площади — 1 000 квадратных метров; реставрационные мастерские — 2 000 квадратных метров; подземные парковочные места; хранилище древностей — 5 000 квадратных метров; ресторан, кафе, библиотека, амфитеатр, офисы, художественный магазин и обширное благоустройство внешних пространств.